Field notes: the week CNY ate two weeks nobody budgeted for

Every January there's a planner somewhere pulling up the same spreadsheet from last year, finding the line where they wrote "CNY: add 10 days," and wondering if that number was ever right to begin with.
It's a reasonable instinct. Factories close for seven to fourteen days depending on the province and the owner's mood about family obligations. Somebody did the math once, built a buffer, and that buffer got copied into every lead time calc since. The problem is the closure was never the thing that cost you time. The two weeks before it, and the two weeks after, are where the slip lives.
Here's what the run-up looks like on the ground. Every factory on your supplier list is trying to get finished goods out the door before the same fourteen-day window, which means every booking desk in the Pearl River Delta is fielding the same request in the same ten-day stretch. Carriers know this is coming and they do what carriers do: they roll cargo, they blank sailings they'd normally run, and they let utilization climb past the point where a late container makes the vessel. Your box misses the boat because three hundred other shippers chased the same cutoff you did, all stacked into the same handful of sailings.
Then the factories close, and for about ten days the lane goes quiet in a way that looks, on paper, like things are running fine: no congestion, no queue, nothing moving. That quiet is a lane holding its breath before the surge hits, nothing more.
The real cost shows up in the three weeks after reopening. Everyone who held cargo for the holiday is now trying to ship it at once, plus the backlog that didn't clear before close, plus whatever got rolled off vessels in the rush. Terminal yards that were empty two weeks ago are suddenly stacked past their working capacity, and dwell times that normally run three or four days start running eight or nine. This is the stretch where a "10 day CNY buffer" quietly becomes 18, and nobody built a line item for it because the spreadsheet only accounted for the factory being shut, not for the three separate traffic jams that bracket it.
I've watched planners handle this two ways. The first group pads harder every year, assuming last year's number undersold it, until the buffer gets so generous it stops meaning anything and procurement starts ignoring it. The second group tries to track it properly, lane by lane, because a closure in Yantian doesn't move the same way as one in Ningbo, and a transpacific lane recovers on a different clock than one feeding into Rotterdam. The yard fill and vessel queue data that would tell you which is which does exist, it's just not sitting in a spreadsheet anyone updates by hand in real time.
That's the whole reason this restart lag is worth watching day by day instead of once a year. The congestion builds and clears on a schedule you can see coming if someone's checking the right terminal and vessel data daily instead of guessing from last year's notes, and Lead Time Risk turns that congestion into a daily slip-day number for the specific lanes you're already watching, so the post-holiday number isn't a guess copied from last year's file.
If your 2027 holiday line item is still "add 10 days" and a shrug, it might be worth checking what the actual slip on your lanes looked like this year before you write next year's number down.